HUD Handbook 4350.3 § 7-6
It is the owner’s responsibility to process all recertifications in a timely manner.
                  HUD Headquarters will terminate *a certification* if a new recertification is not
                  submitted within 15 months of the previous year’s recertification anniversary
                  date. HUD has instructed Contract Administrators to terminate assistance
                  payments to an owner if a new annual recertification has not been completed and
                  submitted through TRACS within 15 months after the previous year’s anniversary
                  date. Owners must repay, by making an adjustment to the voucher, the
                  assistance collected for the 3-month period from the date the annual
                  recertification should have been effective through the end of the 15th month when
                  assistance was terminated. Once the new certification is processed, owners
                  must follow the guidance in paragraph 7-8 for determining the effective date for
                  changes in the TTP, tenant rent and assistance payment when the recertification
                  is delayed.

A.       Owners and tenants must complete the applicable steps listed in Figure 7-3.

         B.       Owners must maintain a tracking system to facilitate timely completion of
                  recertifications.

         C.       To enable owners to give the tenant the required 30-day advance notice of any
                  increase in the TTP or tenant rent, Steps 1 through 6 in Figure 7-3 should be
                  completed at least 35 days before the recertification anniversary date.
Source: Legislative text reproduced verbatim
Plain English

Under HUD Handbook 4350.3 REV-1 CHG-4 § 7-6, annual recertifications for HUD-assisted housing must be completed and submitted through TRACS within 15 months of the prior year's recertification anniversary date. If that deadline is missed, HUD Headquarters may terminate the certification and Contract Administrators may halt assistance payments to the owner. Owners who collected assistance during the lapse period — spanning from when the recertification should have taken effect through the end of the 15th month — are required to repay those amounts by adjusting the voucher. Once the recertification is processed, specific rules govern how changes to tenant rent, total tenant payment (TTP), and assistance amounts are backdated.

Written by anthropic/claude-sonnet-4.6 · Reviewed on September 30, 2026

Plain English — not legal advice.

For Property Managers

Compliant operators under HUD Handbook 4350.3 REV-1 CHG-4 § 7-6 maintain an active tracking system to monitor each tenant's recertification anniversary date and ensure all required steps in Figure 7-3 are completed well in advance. Because tenants must receive at least 30 days' notice before any increase in TTP or tenant rent, Steps 1 through 6 of Figure 7-3 are generally completed no later than 35 days before the anniversary date. Owners who allow a recertification to lapse past the 15-month window face termination of assistance payments and an obligation to repay assistance collected during the 3-month lapse period via a voucher adjustment. After a delayed recertification is processed, paragraph 7-8 of the same handbook governs how effective dates for rent and assistance changes are calculated.

General guidance for property managers — not legal advice for your specific situation. Consult an attorney for advice on your case.

For Tenants

HUD Handbook 4350.3 REV-1 CHG-4 § 7-6 establishes that tenants in HUD-assisted housing are entitled to at least 30 days' advance written notice before any increase in their total tenant payment or tenant rent takes effect. If a tenant believes their owner has failed to complete the annual recertification on time or has not provided proper notice of a rent change, that concern can be raised with the property's Contract Administrator or with HUD directly. Tenants may also contact a local tenant-rights organization for guidance on how recertification delays can affect their assistance and what remedies may be available. Consulting the steps outlined in Figure 7-3, referenced in § 7-6, can help tenants understand what the owner is required to do and when.

General guidance for tenants — not legal advice for your specific situation. Consult a tenant-rights organization or attorney for advice on your case.

Generated September 30, 2026 — auto-generated, not yet human-reviewed. See /transparency for methodology.

Effective Timeline

Expression #1
Sep 24, 2026
Current
Sep 29, 2026
Click on timeline segments to view historical versions.

References Out

No outbound references recorded yet for this provision.

References In

No inbound references recorded yet for this provision.

Related Rules

§ 888.111
§ 888.111 Fair market rents for existing housing: Applicability.
§ 888.201
§ 888.201 Purpose.
§ 888.202
§ 888.202 Manner of publication.

Source Information

Snapshot SHA:
Fetched:Sep 24, 2026, 08:34 PM UTC