Minn. R. 4761 § 4761.2630

METHODS FOR REMOVING INTACT BUILDING COMPONENTS.

In Force
Verified 10/26/2026 · Next check 11/2/2026
effective 9/30/2026MinnesotaRRP

Operative Text

Minn. R. 4761 § 4761.2630
Subpart 1. Applicability; general requirements.
The methods in this part must be used when performing lead hazard reduction to remove intact building components with intact lead-based paint. The removal methods must not disturb the paint or create paint chips or dust. Removing intact building components includes, but is not limited to, removing only a door or window sash from a door or window frame. All work must be completed in one working day.

Subp. 2. Access required.
A person must allow the commissioner to have access to a work site, according to Minnesota Statutes, section 144.99, subdivision 2, while the person performs regulated lead work.

Subp. 3. Work area preparation.
Before lead hazard reduction begins, the floor or ground surface must be cleaned using a vacuum with a HEPA filter to remove all visible paint chips that are present beneath the affected work surface and extending at least five feet beyond the affected surface in all directions.

Subp. 4. Residents.
If residents remain in the residence while work is ongoing, the residents must be provided with lead-safe passage to a bathroom, at least one living area, and an entry and egress route. Unless actually performing lead hazard reduction, residents must not be allowed in the work area until all work is completed, no visible dust or debris remains in the work area, the clearance inspection is passed, and clearance dust samples are collected. The residents must be informed to avoid the work area until clearance results are below the standards under part 4761.2510, subpart 2.

Subp. 5. Warning signs and barriers.
A. Warning signs as required under part 4761.2615, item F, must be placed at the entry to the rooms or work areas where lead hazard reduction is actually occurring.
B. Temporary fencing or barrier tape must be erected at a ten-foot perimeter around an exterior work area to keep out unauthorized persons. The barrier distance may be less if the distance to an adjacent building or sidewalk is less than ten feet.

Subp. 6. Decontamination procedures.
A. The certified lead firm, lead supervisor, or property owner performing lead hazard reduction must provide proper washing facilities for workers to thoroughly wash hands, face, and other exposed body surfaces.
B. If existing facilities are used at the work site to decontaminate, the certified lead firm, lead supervisor, or property owner must:
(1) provide workers with soap and disposable towels; and
(2) clean the existing facility until no visible dust, dirt, or debris remains each day before leaving the site.

Subp. 7. Cleaning procedures and inspection.
When lead hazard reduction is completed, the certified lead firm, lead supervisor, or property owner must:
A. inspect all work surfaces where lead hazard reduction was conducted and visually determine that no suspect lead dust or debris remains in the work area;
B. clean all surfaces within the work area using a vacuum with a HEPA filter or using any other EPA-documented methodology under part 4761.2000, subpart 15, item K, and extend the cleaning beyond the perimeter of the work area if visible dust and debris exists from the lead hazard reduction;
C. clean all floors and ground surfaces in adjacent areas that were used for pathways to the work area and any areas used to store equipment and waste materials using a vacuum with a HEPA filter;
D. visually reinspect all areas referenced in items A to C. If visible dust or debris remains, the cleaning procedures required under items B and C must be repeated; and
E. conduct clearance inspections according to part 4761.2670.
Source: Legislative text reproduced verbatim
Plain English

Minn. R. 4761 § 4761.2630 establishes the specific methods that must be followed when removing intact building components—such as doors or window sashes—that have intact lead-based paint as part of a lead hazard reduction project in Minnesota. The removal process must not disturb the paint or generate chips or dust, and all work must be finished within a single working day. The rule also sets out requirements for work area preparation, resident safety, warning signs, decontamination, and post-work cleaning and clearance inspections.

Written by anthropic/claude-sonnet-4.6 · Reviewed on September 30, 2026

Plain English — not legal advice.

For Property Managers

Property owners overseeing lead hazard reduction work covered by Minn. R. 4761 § 4761.2630 are generally expected to ensure that removal of intact components with lead-based paint is done without disturbing the paint surface, that HEPA vacuuming is completed before and after work, and that the entire job wraps up within one working day. Compliant operators provide workers with proper washing facilities, post required warning signs, and erect barriers around exterior work areas. They also ensure that residents who remain on-site have safe passage to essential areas and are kept out of the work zone until clearance inspections are passed and dust sample results fall below the standards referenced in part 4761.2510, subpart 2.

General guidance for property managers — not legal advice for your specific situation. Consult an attorney for advice on your case.

For Tenants

Under Minn. R. 4761 § 4761.2630, residents have a right to lead-safe passage to a bathroom, at least one living area, and an entry and exit route if they remain in the home during lead hazard reduction work. Residents must be informed to stay out of the work area until clearance results meet the standards set in part 4761.2510, subpart 2, and no visible dust or debris remains. Tenants who believe these protections are not being followed may contact the Minnesota Department of Health, which holds inspection access authority under Minn. Stat. § 144.99, subd. 2, or reach out to a local tenant-rights organization for guidance on available options.

General guidance for tenants — not legal advice for your specific situation. Consult a tenant-rights organization or attorney for advice on your case.

Generated September 30, 2026 — auto-generated, not yet human-reviewed. See /transparency for methodology.

Effective Timeline

Current
Sep 30, 2026
Click on timeline segments to view historical versions.

References Out

Rules and statutes cited by this regulation

Minn. Stat. § 144.99
Not yet ingested
Minn. R. 4761.2510
Not yet ingested
Minn. R. 4761.2615
Not yet ingested
Minn. R. 4761.2000
Not yet ingested
Minn. R. 4761.2670
Not yet ingested

References In

No inbound references recorded yet for this provision.

Related Rules

§ 745.323
§ 745.323 Definitions.
§ 745.326
§ 745.326 Renovation: State and Tribal program requirements.
§ 35.140
§ 35.140 Prohibited methods of paint removal.

Source Information

Snapshot SHA:
Fetched:Sep 30, 2026, 01:17 PM UTC